Topic/Presenter: Budget / Jon Morse Question/Comment: Need more detailed work on budget, setting better numbers where possible, clearly identifying baseline and add-on items, etc. What about contingency? Submitted by: Jon Holtzman NIC-FPS Response: As the opto-mechanical design has matured, we have iterated with vendors to provide higher fidelity budgetary numbers. So far there have been no major surprises. Since the prelimary design review, a redesign of the optics has reducedtheir cost from $100-115K to $75-85K. This has provided some contingency funds. Status: Further details at the Critical Design Review.